Meeting Site Requirements
Extreme Networks BlackDiamond 10K-Series Switch Installation Guide 27
Space Requirements for the Rack
Provide enough space in front of and behind the switch so that you can service it easily. Allow a
minimum of 48 inches (122 cm) in front of the rack and 24 inches (61 cm) behind the rack. When using a
relay rack, provide a minimum of 24 inches (61 cm) of space behind the mounted equipment. Extra
room on each side is optional.
NOTE
Install your equipment rack near an easily accessible power outlet. When you need to disconnect the
power cable from your switch, remove it first from the power source and then from the switch.
Securing the Rack
The rack should be attached to the wiring closet floor with 3/8 inch (9.5 mm) lag screws or equivalent
hardware. The floor under the rack should be level within 3/16 inch (5 mm). Use a floor-leveling
cement compound if necessary or bolt the racks to the floor as shown in Figure 5.
Figure 5: Properly secured rack
Brace open distribution racks if the channel thickness is less than 1/4 inch (6.4 mm).
SPG_007
Secure to floor
with 3/8 inch lag screws or bolts